The VSBK technology outside of China
Several attempts have been made to transfer the VSBK technology from China to other countries

Beginnings in Nepal

IN 1991 under a GTZ_GATE project, a twin-shaft VSBK was constructed at Kathmandu Brick Factory, Lubhu, Nepal. One more VSBK was built in Biratnagar, Nepal. With an energy consumption of 1 MJ per kg of fired bricks, the energy saving potential of the VSBK technology was clearly demonstrated.
However, both kilns ran into early technical problems that the entrepreneurs could not solve unaided. In spite of strong indications that the technology had a great potential, initial enthusiasm was eventually replaced by disappointment and the two Nepalese VSBKs were closed down. The lack of access to reliable technical support was responsible for the failure.
An enthusiastic welcome in Bangladesh

With the assistance of SDC, a brick kiln owner from Bangladesh visited the VSBK units in Nepal. Inspired by what he saw, the entrepreneurs subsequently built a VSBK near Dhaka. Unfortunately, the need for specialized technical assistance was again overlooked. As a consequence, this Bangladeshi pilot plant was never commissioned.

The attempt to transfer know-how to Bangladesh was a spontaneous, private initiative. Unfortunately, the entrepreneur did not know the finer aspects of the technology and without the requisite technical back up; he made fundamental mistakes in the design and construction of his kiln.

Production capacity becomes an issue in Pakistan

In 1993, a VSBK was demonstrated in Peshawar, Pakistan; again under GTZ-GATE development projects. This was followed by construction of several VSBK units in the same region.

In Pakistan, the VSBK demonstration units (with twin shaft design) were marketed as an alternative to Bull’s Trench Kiln (BTK) technology. However, the typical production level of a BTK varies between 15’000 to 50’000 bricks per day in Pakistan. With only two shafts, the VSBK demonstration units could not produce more than 3’000 bricks per day. There was a clear imbalance between output capacity of these dissimilar technologies.

This difference proved to be a major stumbling block in attracting the attention of BTK owners toward VSBK. Inappropriate information on the limits and potentials of VSBK technology resulted in a misjudgment in its marketability. As a consequence of this oversight, the VSBK technology made no significant break-through in Pakistan beyond the early pilot project processes.

Alternative fuels tested in Sudan

A VSBK was adapted for the use in Sudan during 1996. A pilot kiln was constructed by the Building and Road Research Institute (BRRI) of the University of Khartoumin in cooperation with GTZ-GATE. The fuel used was carbonized agricultural waste from cotton stalks, sunflower stalks or bagasse. The carbonized fuel, reduced to a granular size was dispersed among the green bricks when loading the kiln from the top. This VBSK was the first of its kind, which uses carbonized agricultural waste. No recent updates on the operations of the technology are available.

Large scale production in Afghanistan

In 1995, the Pakistan VSBK-GTZ project provided training for engineers and kiln-crews from Herat, Afghanistan in order to construct one 6-shaft VSBK for the Afghanistan Rehabilitation & Energy Conservation Association. Private entrepreneurs constructed three additional 6-shaft VSBK units and a total of 4 such units (i.e. 24 shafts, each of 1m x 1m) were reported to be in operation in 1996. The status of these kilns today is not known.

Commercial success in India - 1997

In 1996, SDC (Swiss Agency for Development and Cooperation) supported an organized transfer of VSBK technology to India through an elaborate Action Research Programme. The process was initiated through a team of local and international experts. This team was commissioned to analyze the mistakes committed in earlier attempts to transfer the VSBK technology beyond its native environment and to identify the success factors responsible for its growth in China. Based on the outcome of the study, a project was formulated for the transfer of the VSBK technology to different geographical regions in India.

The first VSBK kiln was set up in Central India at Datia in Madhya Pradesh. The kiln was based on Chinese designs and was set up in joint partnership with an experienced local brick clamp owner. Initially, a team of experienced Chinese specialists provided on-site operational support services. Local support and key personnel were provided by Development Alternatives to assist in the construction process and operation of the kiln. This pilot kiln confirmed the potential energy savings associated with VSBK and demonstrated the technical feasibility of short cycle brick firing using indigenous soils and fuels.

Buoyed by encouraging results, a second kiln using slightly larger shafts was constructed in Orissa, Eastern India. This was quickly followed by a third kiln for firing extruded bricks, set up in association with (and at the behest of) a reputed manufacturer of fired clay products — COMTRUST in Kerala, South India. All of these early kilns assisted in the building of local capacity for design, construction and operation while demonstrating improved environmental performance. The performance of the kilns was continuously upgraded with the assistance of local partners, consultants and international back stoppers. As of May 2003, more than forty commercial kilns are operational throughout the whole country.

The technology dissemination phase has helped in paving the way for a purely commercial multiplication process in India through various agencies the prime being Development Alternatives.

Successful introduction in Vietnam - 2001

An UNDP project funded by “Small Grant Programme of the Global Environment Fund” introduced the first ever VSBK in Vietnam in 2001. The VSBK was constructed under the supervision of Chinese experts and the VSBK became operational in December, 2001.

After the successful operation of this VSBK, about one hundred VSBKs were built across Vietnam in a short period of two years. However, most of the VSBKs were self copied without proper design and construction advice from experts, which resulted into complication in operation, uneven shaft size and excess flue gas on the top of the loading platform. However, the Ministry of Science and Technology awarded a gold medal to a VSBK company for energy saving and environmental performance in December, 2003.

This clearly indicates that if the VSBK technology is properly transferred, the VSBK technology know-how locally anchored, there is an immense potential to transfer and bride the existing traditional brick making system into an environmental cleaner future.

Reintroduction of VSBK in Nepal - 2003


Technical problems faced during the initial introduction of the VSBK technology in Nepal in 1991 were solved during a nearly 10 yearlong technology development phase concentrated mainly in India. Thus a global VSBK technology dissemination potential was realized.

The growing concern of environmental pollution resulted from brick production in Kathmandu Valley made it an urgent issue to change the prevailing BTK firing process with an environmentally accepted brick firing technology. The VSBK technology, after a commercial success with more than 40 operating kilns in India, was an obvious choice.

A feasibility study, conducted by Skat Consulting in 2002, confirmed the commercial potential of VSBK with a general positive impact on the environment. Thus a VSBK Technology Transfer Programme in Nepal was signed between Swiss Development Agency and HMG, Nepal in February 2003 for reintroducing it in Kathmandu Valley.

The introduction strategy of the VSBK technology to Nepal includes a demonstration phase that is presently being implemented. During this phase two pilot kilns have already been constructed. Brick quality, environmental and energy performance confirmed previous efforts, notably from India. An economic study as well as feed backs from entrepreneurs proof the economic viability of the new technology in the Nepali context. The long term technical support required by future entrepreneurs has been ensured through a local network of commercially operating support service providers trained by the VSBK programme.